Energy Power Plant

Energy Power Plant

Location
Tatlıpınar / Balıkesir
License Date and Validity Period
21.06.2012 - 48 years, 7 months, 24 days
Date of Commissioning
5 türbin (19,5 MW): Kasım 19, 20 türbin (96 MW) : Aralık 20-Haziran 21
Status of Land Ownership
All permits have been completed.
Contribution Margin
4,47 kr/kWh
Installed Power (MW)
115,5
WPP Capacity Increase (MW)
33,6 MW
After Capacity Increase
607.000 MWh
Turbine Brand and Model
5 adet Nordex N131 3,9 MW, 20 adet Nordex N149 4,8 MW
Turbine Hub Height
114 m (3.9 MW) / 105 m (4.8 MW)
Average Wind Speed (m/sec)
7,2 (m/sn)
Annual Electricity Generation
392,0 GWh
Capacity Factor
% 38,7
SPP Capacity Increase (MW)
79 MW
After Capacity Increase
228,1 MW